Distribution centre conveyors
Conveyor retrofit and sortation logic for a peak-season distribution centre.
Headline result
2.1×
Peak throughput
Orders / hour
1.8k
3.8k
+111%
Mis-sorts
1.2%
0.3%
−75%

The challenge
A regional distribution centre could not ship its peak-season volume. The conveyor loop jammed at the sorter merge, and mis-sorted totes were sent back by hand.
What we did
We modelled the flow with a year of real order data, added accumulation buffers before the merge and rewrote the sortation logic so totes are released in waves.
The retrofit went in over three weekends, without losing a shipping day.
The result
Peak throughput went from 1,800 to 3,800 orders an hour in the same building, and mis-sorts fell from 1.2% to 0.3%.